A review of causes of delay in construction projects

  • Authors

    • Mohammad Al-Mohammad University Malaysia Pahang
    • Omar Bin Jamaludin University Malaysia Pahang
    2019-03-12
    https://doi.org/10.14419/ijet.v7i4.19506
  • Causes of Delay, Construction Projects, Risk Management, Time Overrun.
  • Abstract

    Time is one of the keys by which project success can be measured. However, delay in construction projects remains a common occurrence. This paper attempts towards reviewing past literature on causes of delay in different types of construction. The most common methods adopted by researchers for causes of delay identification were presented. This review also discussed the groups causing delay based on the source of delay. The top five delay factors related to contractor, owner and consultant have been discussed within each category. This paper revealed that previous researches are regarded as the main source for causes of delay identification. Moreover, questionnaire and the relative importance index are the most frequent methods for collecting data and ranking delay factors, respectively. Contractor, owner and consultant groups are the highest frequent groups utilized for categorization. Furthermore, causes of delay related to contractor and owner are of great importance. While consultant group and its relevant causes have shown lesser importance relatively.

     

     

  • References

    1. [1] I. Mahamid, A. Bruland, and N. Dmaidi, “Causes of delay in road construction projects," Journal of Management in Engineering, vol.28, no.3, (2012), pp 300–310, available online: https://doi.org/10.1061/(ASCE)ME.1943-5479.0000096.

      [2] S. Y. Tesfa, “Analysis of factors contributing to time overruns on road construction projects under Addis Ababa City Administration,†International Journal of Science and Research, vol.5, no.7, (2016), pp. 2181–2187, available online: https://www.ijsr.net/archive/v5i7/ART2016615.pdf.

      [3] S. A. Assaf and S. Al-Hejji,“Causes of delay in large construction projects,†International Journal of Project Management, vol. 24, no. 4, (2006), pp. 349–357. https://doi.org/10.1016/j.ijproman.2005.11.010.

      [4] M. J. Kamanga and W. J. V. D. M. Steyn, “Causes of delay in road construction projects in Malawi,†Journal of the South African Institution of Civil Engineering, vol. 55, no. 3, (2013), pp. 79–85.

      [5] G. J. Sweis, “Factors affecting time overruns in public construction projects: The case of jordan,†International Journal of Business and Management, vol. 8, no. 23, (2013), pp. 120–129, available online: https://doi.org/10.5539/ijbm.v8n23p120.

      [6] A. Suwal and S. K. Shrestha, “Causes of delays of motorable bridge construction under postal highway projects, Department of Roads,†Journal of Advanced College of Engineering and Management, vol. 2, (2016).

      [7] A. Kazaz, S. Ulubeyli, and N. A. Tuncbilekli, “Causes of delays in construction projects in Turkey,†Journal of Civil Engineering and Management, vol. 18, no. 3, (2012), pp. 426–435, available online: https://doi.org/10.3846/13923730.2012.698913.

      [8] S. M. El-Sayegh, “Risk assessment and allocation in the UAE construction industry,†International Journal of Project Management, vol. 26, no. 4, (2008), pp. 431–438, available online: https://doi.org/10.1016/j.ijproman.2007.07.004.

      [9] Y. Rahsid, S. Haq, and M. S. Aslam, “Causes of delay in construction projects of Punjab-Pakistan : An empirical study,†Journal of Basic and Applied Scientific Research, vol. 3, no. 10, (2013), pp. 87–96.

      [10] S. K. Patil, A.K.Gupta, D. B. Desai, and A.S..Sajane, “Causes of delay in Indian transportation infrastructure projects,†International Journal of Research in Engineering and Technology, vol. 2, no. 11, (2013), pp. 71–80. https://doi.org/10.15623/ijret.2013.0211013.

      [11] D. A. Obodoh, “Causes and effects of construction project delays in Nigerian construction industry,†International Journal of Innovative Science, Engineering & Technology, vol. 3, no. 5, (2016), pp. 65–84.

      [12] R. F. Aziz and A. A. Abdel-Hakam, “Exploring delay causes of road construction projects in Egypt,†Alexandria Engineering Journal, vol. 55, no. 2, (2016), pp. 1515–1539, available online: https://doi.org/10.1016/j.aej.2016.03.006.

      [13] H. Adnan, K. Jusoff, and M. K. Salim, “The Malaysian construction industry’s risk management in design and build,†Modern Applied Science, vol. 2, no. 5, (2008), pp. 27–33, available online: https://doi.org/10.5539/mas.v2n5p27.

      [14] S. M. Renuka, C. Umarani, and S. Kamal, “A review on critical risk factors in the life cycle of construction projects,†Journal of Civil Engineering Research, vol. 4, no. 2A, (2014), pp. 31–36, available online: doi:10.5923/c.jce.201401.07.

      [15] D. A. R. Dolage and D. L. G. Rathnamali, “Causes of time overrun in construction phase of building projects: A case study on Depatrment of Engineering Services of Sabaragamuwa Provincial Council,†Engineer, vol. XXXXVI, no. 03, (2013), pp. 9–18, available online: https://doi.org/10.4038/engineer.v46i3.6780.

      [16] G. S. A. Elawi, M. Algahtany, and D. Kashiwagi, “Owners’ perspective of factors contributing to project delay: Case studies of road and bridge projects in Saudi Arabia,†in Procedia Engineering, vol. 145, (2016), pp. 1402–1409. https://doi.org/10.1016/j.proeng.2016.04.176.

      [17] M. Alzara, J. Kashiwagi, D. Kashiwagi, and A. Al-Tassan, “Using PIPS to minimize causes of delay in Saudi Arabian construction projects: University case study,†in Procedia Engineering, vol. 145, no. 480, (2016), pp. 932–939. https://doi.org/10.1016/j.proeng.2016.04.121.

      [18] S. Hussain, F. Zhu, Z. Ali, H. D. Aslam, and A. Hussain, “Critical delaying factors: Public sector building projects in Gilgit-Baltistan, Pakistan,†Buildings, vol. 8, no. 6, (2018), pp. 1–16, available online: https://doi.org/10.3390/buildings8010006.

      [19] I. Mahamid, “Risk matrix for factors affecting time delay in road construction projects: owners’ perspective,†Engineering, Construction and Architectural Management, vol. 18, no. 6, pp. 609–617, available online:

      [20] M. A. Othuman Mydin, N. M. Sani, M. Taib, and N. Mohd Alias, “Imperative causes of delays in construction projects from developers’ outlook,†MATEC Web Conferences, vol. 10, no. 06005, (2014), pp. 1–5, available online: https://doi.org/10.1051/matecconf/20141006005.

      [21] I. Mahamid, “Common risks affecting time overrun in road construction projects in palestine: Contractors’ perspective,†Australasian Journal of Construction Economics and Building, vol. 13, no. 2, (2013), pp. 45–53. https://doi.org/10.5130/AJCEB.v13i2.3194.

      [22] K. Khair, H. Farouk, Z. Mohamed, and R. Mohammad, “Causes and effects of delay factors in road construction projects in Sudan,†International Journal of Applied Engineering Research, vol. 11, no. 18, (2016), pp. 9526–9533, 2016.

      [23] M. Atibu Seboru, “An investigation into factors causing delays in road construction projects in Kenya,†American Journal of Civil Engineering, vol. 3, no. 3, (2015), pp. 51–63, available online: https://doi.org/10.11648/j.ajce.20150303.11.

      [24] J. M. Assbeihat, “Factors affecting delays on private construction projects,†International Journal of Civil Engineering and Technology, vol. 7, no. 2, (2016), pp. 22–33, available online : http://www.iaeme.com/IJCIET/issues.asp?JType=IJCIET&VType=7&IType=2.

      [25] S. U. R. Toor and S. Ogunlana, “Problems causing delays in major construction projects in Thailand,†Construction Management and Economics, vol. 26, no. 4, (2008), pp. 395–408, available online: https://doi.org/10.1080/01446190801905406.

      [26] D. S. Santoso and S. Soeng, “Analyzing delays of road construction projects in Cambodia: Causes and effects,†Journal of Management in Engineering, vol. 32, no. 6, (2016), p. 05016020-1-05016020-11, available online: https://doi.org/10.1061/(ASCE)ME.1943-5479.0000467.

      [27] H. Doloi, A. Sawhney, K. C. Iyer, and S. Rentala, “Analysing factors affecting delays in Indian construction projects,†International Journal of Project Management, vol. 30, no. 4, (2012), pp. 479–489, availble online: https://doi.org/10.1016/j.ijproman.2011.10.004..

      [28] M. Khoshgoftar, A. H. A. Bakar, and O. Osman, “Causes of delays in Iranian construction projects,†Int. J. Constr. Manag., vol. 10, no. 2, pp. 53–69, 2010. https://doi.org/10.1080/15623599.2010.10773144.

      [29] M. M. Marzouk and T. I. El-Rasas, “Analyzing delay causes in egyptian construction projects,†Journal of Advanced Research, vol. 5, no. 1, (2014), pp. 49–55, available, online: https://doi.org/10.1016/j.jare.2012.11.005.

      [30] R. F. Aziz, “Ranking of delay factors in construction projects after Egyptian revolution,†Alexandria Engineering Journal, vol. 52, no. 3, (2013), pp. 387–406, availble online: https://doi.org/10.1016/j.aej.2013.03.002.

      [31] Q. K. Jahanger, “Important causes of delay in construction projects in Baghdad city,†Australian Journal of Basic and Applied Sciences, vol. 7, no. 4, (2013), pp. 14–23, 2013.

      [32] A. Arantes, P. F. Da Silva, and L. M. D. F. Ferreira, “Delays in construction projects - Causes and impacts,†in Proceedings of International Conference on Industrial Engineering and Systems Management, (2015), Seville, Spain. https://doi.org/10.1109/IESM.2015.7380293.

      [33] M. H. Fallahnejad, “Delay causes in Iran gas pipeline projects,†International Journal of Project Management, vol. 31, no. 1, (2013), pp. 136–146, available online: https://doi.org/10.1016/j.ijproman.2012.06.003.

      [34] M. Sambasivan and Y. W. Soon, “Causes and effects of delays in Malaysian construction industry,†International Journal of Project Management, vol. 25, no. 5, (2007), pp. 517–526, available online: https://doi.org/10.1016/j.ijproman.2006.11.007.

      [35] L. Van Truong, N. M. Sang, and N. T. Viet, “A conceptual model of delay factors affecting government construction projects,†ARPN Journal of Science and Technology, vol. 5, no. 2, (2016), pp. 92–100.

      [36] Z. Shehu, I. R. Endut, and A. Akintoye, “Factors contributing to project time and hence cost overrun in the Malaysian construction industry,†Journal of Financial Management of Property and Construction, vol. 19, no. 1, (2014), pp. 55–75, https://doi.org/10.1108/JFMPC-04-2013-0009.

      [37] A. S. Faridi and S. M. El-Sayegh, “Significant factors causing delay in the UAE construction industry,†Construction Management and Economics, vol. 24, no. 11, (2006), pp. 1167–1176, available online: https://doi.org/10.1080/01446190600827033.

      [38] M. E. Abd El-Razek, H. A. Bassioni, and A. M. Mobarak, “Causes of delay in building construction projects in Egypt,†Journal of Construction Engineering and Management, vol. 134, no. 11, (2008), pp. 831–841, available online: https://doi.org/10.1061/(ASCE)0733-9364(2008)134:11(831).

      [39] A. H. Memon, I. Abdul Rahman, M. R. Abdullah, and A. A. Abdul Azis, “Time overrun in construction projects from the perspective of project management consultant ( PMC ),†Journal of Surveying, Construction & Property, vol. 2, no. 1, (2011), pp. 54–66. https://doi.org/10.22452/jscp.vol2no1.4.

      [40] B. I. Al Hadithi, “An investigation into factors causing delays in highway construction projects in Iraq,†in MATEC Web of Conferences, (2018), vol. 162, available online: https://doi.org/10.1051/matecconf/201816202035.

      [41] Z. Rachid, B. Toufik, and B. Mohammed, “Causes of schedule delays in construction projects in Algeria,†International Journal of Construction Management, (2018), available online: https://doi.org/10.1080/15623599.2018.1435234.

      [42] S. K. Pawar and S. S. Ambure, “An assessment of the factors causing delays on residential construction projects in Pune,†International Journal of Science and Research, vol. 6, no. 6, (2017), pp. 2319–2323.

      [43] S. K. Pai and M. J. R. Bharath, “Analysis of critical causes of delays in Indian infrastructure projects,†International Journal of Innovative Research & Development, vol. 2, no. 3, (2013), pp. 251–263.

      [44] I. Mahamid, “Risk matrix for factors affecting time delay in road construction projects: Consultants’ perspective,†Applied Mechanics and Materials, vol. 147, (2011), pp. 244–248, available online: https://doi.org/10.4028/www.scientific.net/AMM.147.244.

      [45] A. H. Alavifar and S. Motamedi, “Identification, evaluation and classification of time delay risks of construction project in Iran,†in International Conference on Industrial Engineering and Operations Management, (2014), Bali, Indonesia, pp. 919–929.

      [46] R. Hasan, S. Suliman, and Y. Al Malki, “An investigation into the delays in road projects in Bahrain,†International Journal of Research in Engineering and Science, vol. 2, no. 2, (2014), pp. 38–47.

      [47] O. Motaleb and M. Kishk, “An Investigation into the risk of construction projects delays in the UAE,†International Journal of Information Technology Project Management, vol. 4, no. 3, (2013), pp. 50–65, 2.

      [48] Y. Amare, E. T. Quezon, and M. Busier, “Causes of delays during construction phase of road projects due to the failures of contractor, consultant, And employer in Addis Ababa City Road Authority,†International Journal of Scientific & Engineering Research, vol. 8, no. 3, (2017), pp. 15–25.

      [49] A. H. Memon, I. A. Rahman, M. Akram, and N. M. Ali, “Significant factors causing time overrun in construction projects of Peninsular Malaysia,†Modern Applied Science, vol. 8, no. 4, (2014), pp. 16–28, available online: https://doi.org/10.5539/mas.v8n4p16.

  • Downloads

  • How to Cite

    Al-Mohammad, M., & Bin Jamaludin, O. (2019). A review of causes of delay in construction projects. International Journal of Engineering & Technology, 7(4), 5078-5083. https://doi.org/10.14419/ijet.v7i4.19506

    Received date: 2018-09-11

    Accepted date: 2019-02-17

    Published date: 2019-03-12