A Review of Leadership Qualities among Building Refurbishment Project Managers
-
2018-11-30 https://doi.org/10.14419/ijet.v7i4.22.27863 -
Building refurbishment project, uncertainty factors, leadership qualities, project manager, project performance -
Abstract
This paper provides a review of potential leadership qualities among building refurbishment project managers. The scope of work in refurbishment projects is very much different to that of new building projects. The key features associated with refurbishment projects are that they are unique, risky, highly complex, and inherently filled with uncertainties that are constant throughout the project’s lifecycle. Furthermore, these projects have always been identified with poor project performance that encompasses time, cost, and quality aspects. Despite the greater attention received in recent years, most previous research that provided solutions for the poor performance issues had narrowly focused on technical measures instead of human impact elements. Consequently, leadership qualities amongst project managers were not examined. This study aims to identify potential leadership qualities among building refurbishment project managers. In addition, the relationships between uncertainty factors and performance of refurbishment projects as mediated by the leadership qualities will also be determined. To achieve this aim, a literature search was conducted and relevant articles reviewed from 1997 to 2017. Initially, 125 articles were identified. However, only 70 articles remained after the second stage of the screening process. Arising from this review, a research model was proposed. This model serves as the basis for extended research on leadership qualities among project managers to better manage uncertainties in refurbishment projects.
Â
-
References
[1] Rahmat, I. Managing Refurbishment Projects. University Publication Centre (UPENA) UITM. Shah Alam 2008.
[2] Rahmat, I. Bin, & Adnan, H. Planning for Refurbishment Projects : the Effects of Organizational Complexity and Integration. 2012. 7(5), 554–560.
[3] Ali, A. S. Complexity in Managing Refurbishment Design Process: Malaysian Experience. MATEC Web of Conferences. 2014. 15, 1030. https://doi.org/10.1051/matecconf/20141501030.
[4] Bonacina, C. F., Malighetti, L., & Pizzi, E. INNOVATIVE DESIGN TOOLS FOR SUSTAINABLE stock Research method 16. 2013.Retrievedfromhttp://cesb.cz/cesb13/proceedings/1_refurbishment/CESB131211.pdf
[5] CIDB. Laporan tahunan 2014. Retrieved from http://www.cidb.gov.my/cidbv4/images/pdf/2016/FA CIDB Annual Report 2014_Publish.pdf. 2014.
[6] Ali, A, S, Kamaruzzaman, S., Zulkiflee, A., & Pitt, M. A Study on Design Performance of Refurbishment Projects in Malaysia. 2010. (November), 323–329. https://doi.org/10.3130/jaabe.9.323
[7] Ali, A. S., Kamaruzzaman, N. S., & Salleh, H. The characteristics of refurbishment projects in Malaysia. Facilities. 2009. 27(1/2), 56–65. https://doi.org/10.1108/02632770910923090
[8] Ali, S. A., Smith, A., Pitt, M., & Choon, C. H. Contractor’s Perception of Factors Contributing To Project Delay: Case Studies Of Commercial Projects in Klang Valley, Malaysia. Journal of Design and Build Environment. 2012. 7(1), 17.
[9] Yacob, R., Rahmat, I., Saruwono, M., & Ismail, Z. EFFECTS OF UNCERTAINTY FACTORS AND REFURBISHMENT PROJECTS PERFORMANCE IN RELATION TO LEADERSHIP QUALITY OF PROJECT MANAGERS. Journal of Building Performance. 2017. 8(1), 2180–2106. Retrieved from http://spaj.ukm.my/jsb/index.php/jbp/index
[10] Rahmat, I. The Planning and Control Process of Refurbishment Projects. Journal of Chemical Information and Modeling. 1997. 53(9),1689–1699.http://doi.org/10.1017/CBO9781107415324.004
[11] Sunikka-blank, M., Chen, J., & Britnell, J. Improving Energy Efficiency of Social Housing Areas : A Case Study of a Retrofit Achieving an “ A †Energy Performance Rating in the UK Improving Energy Efficiency of Social Housing Areas : A Case Study of a Retrofit Achieving an “ A †Energy Performance. European Planning Studies, (June 2012), 37–41.
[12] Jens. International Public Organisations Uncertainty + Complexity Today’s Reality for Leaders in International Public Organisations. 2013.
[13] Berg, M. E., & Karlsen, J. T. Managing Stress in Projects Using Coaching Leadership Tools. Engineering Management Journal. 2013. 25(4), 52–61. https://doi.org/10.1080/10429247.2013.11431995.
[14] Nilsson, I. L. Leadership in crisis, chaos and conversion: An empirical study of business and management executives. S. Academiae Ubsaliensis. 2001.
[15] Hodgson, P., White, R., & White, R. FACING THE UNKNOWN: WHAT ARE LEADERS FOR IF NOT TO MANAGE UNCERTAINTY? 2003. Retrieved September 12, 2016, from http://iveybusinessjournal.com/publication/facing-the-unknown-what-are-leaders-for-if-not-to-manage-uncertainty/
[16] Dick, B. Leadership & Improving Team Performance. 2015. Retrieved May 29, 2016, from http://4pm.com/leading-project-teams-4pm-com/
[17] Jaeger. Adair. Human factors simulation in construction management education.ResearchGa. 2010. Retrieved from https://www.researchgate.net/publication/245494223_Human_factors_simulation_in_construction_management_education
[18] Egbu, C, O. Skills, knowledge and competencies for managing construction refurbishment works. Journal of Construction Management and Economics. 1999. 17, 29–43.
[19] Quah. L.K. Comparative variability in tender bids for refurbishment and new build work. Journal of Construction Management and Economics. 1992. 10., 263–269.
[20] Rahmat, I., & Ali, A. S. The involvement of the key participants in the production of project plans and the planning performance of refurbishment projects. Journal of Building Appraisal. 2010. 5(3), 273–288. https://doi.org/10.1057/jba.2009.34
[21] Saurin, T. A., Rooke, J., Koskela, L., & Kemmer, S. Guidelines for the Management of Complex Socio-Technical Systems: An Exploratory Study of A Refurbishment Project. 2013. Iglc-21, (July), 13–22.
[22] Galbraith, J. R. Organization design: An information processing view. Organizational Effectiveness Center and School. 1997. 21(1), 21–26. https://doi.org/10.1287/inte.4.3.28
[23] Ward, S., & Chapman, C. Transforming project risk management into project uncertainty management. International Journal of Project Management. 2003. 21(2), 97–105. https://doi.org/10.1016/S0263-7863(01)00080-1
[24] Egbu, C. O., Young, B. A., & Torrance, V. B. Planning and control processes and techniques for refurbishment management. Construction Management and Economics. 1998. 16(3), 315–325. https://doi.org/10.1080/014461998372349
[25] Ekung, S., & Onwusonye, S. INVESTIGATING THE USE OF UNCERTAINTY MANAGEMENT TOOLS AND TECHNIQUES WITHIN THE CONSTRUCTION SECTOR. 2015. 2(1), 13–27.
[26] Ali, A. S. Design information in managing refurbishment projects in Malaysia. International Journal of the Physical Sciences, 2010. 5(6), 768–773. Retrieved from http://www.academicjournals.org/IJPS
[27] Ali, A. S., & Zakaria, R. Complexity of statutory requirements: case study of refurbishment projects in Malaysia. Journal of Building Performance. 2012. 3(1), 49–54. Retrieved from http://spaj.ukm.my/jsb/index.php/jbp/article/view/54/0
[28] MCKim, Terek, R., & Attalia, M. Project Performance Control in Reconstruction Project. Journal of Construction Engineering and Management. 2000, 126(2), 137–141.
[29] Karlsson, E., & Svensson, M. The Refurbishment Process From of a sustainability and energy efficient point of view. 2015. 0(vx). Retrieved from http://hj.diva-portal.org/smash/get/diva2:873035/FULLTEXT01.pdfThomas
[30] Josephson, P. E., & Lindstrom, J. Measuring Performance in Construction Projects. Proceeding of the CIB World Building Conference on Construction for Development. Cape Town, South Africa. 2007. pp 383-394.
[31] Thomas, S.R., Macken, C.L., Chung, T. H., & Kim, I. Measuring the Impact of the Delviery System on Project Performance: Deisgn-Build and Design-Bid-Build. Construction Industry Institute. Austin. 2002. 02–840.
[32] Mokhtar, S. N. Identifying Activities That Contribute To The Generation of Refurbishment Waste At Site Identifying Activities That Contribute To The Generation of Refurbishment Waste At Site. 2015. (April). http://doi.org/10.13140/RG.2.1.1122.3765Tang
[33] Tang, Z., & Ng, S. T. Sustainable Building Development in China – A System Thinking Study. Procedia Engineering. 2014. 85, 493–500. http://doi.org/10.1016/j.proeng.2014.10.576
[34] De Haan, T., Jansen, P., & Lighart, P. Sustainable Leadership: Talent requirement for sustainable enterprises. (2015).
[35] Cohen, M. D., & March, J. G. Leadership and Ambiguity: The American College President. McGraw-Hill Book Company, Hightstown, New Jersey 08520 ($10.00). 1974.
[36] Murphy, E. C. Leadership IQ: A Personal Development Process Based on a Scientific Study of a New Generation of Leaders (1 edition). Wiley. 1996. Retrieved from https://www.amazon.com/Leadership-IQ-Development-Scientific-Generation/dp/0471147125
[37] Den Hartog, D. N., De Hoogh, A. H. B., & Keegan, A. E. The interactive effects of belongingness and charisma on helping and compliance. Journal of Applied Psychology. 2007. 92(4), 1131–1139. https://doi.org/10.1037/0021-9010.92.4.1131
[38] Ain, N., Nasaruddin, N., & Rahman, I. A. Leadership Quality for Malaysia Construction Leader to Steer a Success Construction Project, 6, 0–4. 2016. Retrieved from http://www.matec-confces.org/articles/matecconf/pdf/2016/10/matecconf_iconcees2016_04006.pdf
[39] Montequin, V. R., Nieto, A. G., Ortega, F., & Villanueva, J. Managerial Style Profiles of Successful Project Managers: A Survey. Procedia Computer Science. 2015. 64, 55–62. https://doi.org/10.1016/j.procs.2015.08.463
[40] Udhayakumar and P. Karthikeyan. (2014). Expected leadership qualities for a project manager to manage construction project site. Int. J. of Innovative Research and Development, 3, 57-61, (2014).
[41] Bruna, M. The Leader as a Mensch: Become the Kind of Person Others Want to Follow. 2009.
[42] Hanna, A. S., Ibrahim, M. W., Lotfallah, W., Iskandar, K. A., & Russell, J. S. Modeling Project Manager Competency: An Integrated Mathematical Approach. Journal of Construction Engineering and Management. 2016. 142(8), 4016029. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001141
[43] Stuart Duff. Leadership in times of uncertainty | Training Journal. 2016. Retrieved from https://www.trainingjournal.com/articles/feature/leadership-times-uncertainty
[44] Chamorro, T., Seymour, A., & Kaiser, R. B. What Science Says About Identifying High-Potential Employees? Havard Business. 2017. Review. Retrieved from https://hbr.org/2017/10/what-science-says-about-identifying-high-potential-employees
[45] Egbu, C. O. Skills, knowledge and competencies for managing construction refurbishment works. Construction Management and Economics. 2010. 17(1), 29–43. https://doi.org/10.1080/014461999371808
[46] Cooper, B. K. An Introduction to Moderated Mediation. 2015. Retrieved from https://www.deakin.edu.au/__data/assets/pdf_file/0005/432068/Moderated-mediation.pdf
[47] Bradberry, T. 11 strategies successful leaders use to overcome uncertainty. 2015. Retrieved September 12, 2016, from https://www.weforum.org/agenda/2015/09/11-strategies-successful-leaders-use-to-overcome-uncertainty/
[48] Thylin, K. Leadership in situations of uncertainty. 2009.
[49] Ali, A. S., Peng, C., Yong, A. L., & Chieng, S. Managing Refurbishment Projects through Selection of Procurement System: The Case of Malaysia. European Journal of Sustainable Development. 2014. 3(4), 311–322. http://doi.org/10.14207/ejsd.2014.v3n4p311.
[50] Ali, A. S., Rahmat, I., & Noordin, N. Uncertainty in the design process. 2007. Micra, 1–10.
[51] Baldwin, A. N., Austin, S. A., Hassan, T. M. and Thorpe. Modeling information flow during the conceptual and schematic stages of building design, Journal of Construction Management and Economics, 1999. Vol.17, 155-167.
[52] Harris, C. M. Interior fit out of commercial office space, CPD Talk, The Chartered Institute of Building, November, Malaysia. 2006.
[53] Stone, P.A. Building economy, Pergamon press, Oxford. 1976.
[54] Laufer A., Denker, G. And Shenhar, A. “Simultaneous management: the key to excellence in capital project, International Journal of Project Management, Vol.14, Elsevier Science Ltd and IPMA, UK. 1996.
[55] Christiansen, F. The Planning Process at a Construction Site. 2012. Retrieved from http://vpp.sbuf.se/Public/Documents/ProjectDocuments/d1b10c57-fda7-41ec-a113-d76d471cf61d/FinalReport/SBUF 12297 Slutrapport Identifier a triggers.pdf
[56] Shah, S Sustainable Refurbishment (1st ed., Vol. 1). Wiley-Blackwell. 2012. ISBN: 978-1-4051-9508-9. http://doi.org/10.1017/CBO9781107415324.004
[57] Strachan, M. Energy-led, non-domestic building refurbishment : Decision support for a whole-building approach to improvement of operational performance. 2013. Retrieved from http://www.ros.hw.ac.uk/bitstream/handle/10399/2724/StrachanM_0713_sbe.pdf?sequence=1&isAllowed=y
[58] Mitropoulos, P., & Howell, G. A. Journal of management in engineering. Journal of Management in Engineering (Vol. 18). American Society of Civil Engineers. 2002. Retrieved from https://trid.trb.org/view/727097
[59] Quah, L. K. An Evaluation of the risks in estimating and tendering for refurbishment work. PhD thesis, Herriot Watt University, Edinburgh, UK. 1988.
[60] Daoud. The Architect/Engineer’s role in rehabilitation work, Journal of Construction Engineering and Management. 1997. Vol. 123, No. 1, 1- 5
[61] Rosli Abdul Rashid, Ismail Mat Taib , Wan Basiron Wan Ahmad, Md. Asrul Nasid, Wan Nordiana Wan Ali &Zainab Mohd Zainordin. Effect of procurement systems on the performance of construction projects. Department of Quantity Surveying, Faculty of Built Environment, Universiti Teknologi Malaysia. 2006.
[62] Okoroh, M.C. Knowledge-based decision support system for the selection and appointment of subcontractors for building refurbishment contracts. PhD thesis, Loughbourough University,Loughbourough. 1992.
[63] Holm, M.G. Service management in housing refurbishment: a theoretical approach.Journal of Construction Management and Economics. 2000. Vol. 18, 525-533.I
[64] Oke, Adegoke, Natasha Munshi, and Fred O. Walumbwa. 2008. “The Influence of Leadership on Innovation Processes and Activities.†Organizational Dynamics 38 (1): 64-72. DOI: 10.1016/j.orgdyn. 2008.10.005.
[65] Bass, Bernard. M. and Ruth Bass. The Bass Handbook of Leadership: Theory, Research, and Managerial Application. 4th ed. New York. Free Press. 2009.
[66] Levine, Kenneth J., Robert A. Muenchen, and Abby M. Brooks. “Measuring Transformational and Charismatic Leadership: Why Isn’t Charisma Measured?†Communication Monographs 77 (4): 576-591. DOI: 10.1080/03637751.2010.499368. 2010.
[67] D’Amato, A. & Roome, N. “Toward an Integrated Model of Leadership for Corporate Responsibility and Sustainable Development: A Process Model of Corporate Responsibility beyond Management Innovation.†Corporate Governance: International Journal of Business and Society, 9, 421–434. 2009.
[68] Crane, A. & Matten, D. Business Ethics, a European Perspective: Managing Corporate Citizenship and Sustainability in the Age of Globalization. New York, NY: Oxford University Press. 2004.
[69] Hind, P., Wilson, A. & Lenssen, G. “Developing leaders for sustainable business.†Corporate Governance, 9, 7–20. 2009.
[70] Noori, A., Saruwono, M., & Adnan, H. InCIEC 2016. http://doi.org/10.1007/978-981-10-0155-0
-
Downloads
-
How to Cite
Yacob, R., Saruwono, M., & Ismail, Z. (2018). A Review of Leadership Qualities among Building Refurbishment Project Managers. International Journal of Engineering & Technology, 7(4.22), 126-131. https://doi.org/10.14419/ijet.v7i4.22.27863Received date: 2019-02-24
Accepted date: 2019-02-24
Published date: 2018-11-30